Herlong PUD is accepting proposals for 3 wire fencing around 640 acres.
SUMMARY: Herlong PUD is accepting proposals for 3 wire fencing around the wastewater plant in Herlong CA, approximately 21000 feet.
BIDDERS: The District will accept bids until July 1ˢᵗ at 4:00p.m. We require all bidders to clearly represent their subcontracting intentions, if any. All documents must be prepared and signed by those authorized to do so. All costs must be listed in US dollars.
PROJECT AND SCOPE: The purpose of the fencing is to help keep trespassers out and as much dumping as possible.
PROPOSAL TIMELINE AND PROJECT DEADLINE: Proposals are due by 7/1/2026 at 4:00p.m. and project to be completed by 12/31/2026.
BUDGET REQUIREMENTS: Each proposal shall include a brief description of the company or past jobs completed. Include for consideration:
- Cost of Materials
- Cost of Labor
- Overhead
- Total Project Cost
Herlong PUD will evaluate proposals based on overall cost, experience, references.
The Herlong PUD Board will complete review of the proposal at the July 28ᵗʰ board meeting and send out letters to proceed within 3 days.
Contact: Sandy Raffelson, GM at 1.530.827.3150 or email [email protected] with any questions or if you want a copy of the property boundaries being fenced.